Top view
2x8 fir joists
roof/floors
4' cantilever O.H.
above 4' decks below.
each deck is the roof/ceiling of the next deck.
exterior walls
Side view, 3 levels showing for clarity of design, 5 decks in reality.
Living area
Living area
Living area
exterior wall
Floor joists 2 x 8 Fir
Roof joists/rafters 2 x 8 Fir
HLL anchor point - FALLTECH BOLT-ON D-RING ANCHOR - center 2x8 joist, 1' from wall
HLL safety line -
80' max span re manufacturer specs
7.7" max sag at center re manufacturer specs
HLL anchor point -
FALLTECH BOLT-ON D-RING ANCHOR - center 2x8 joist, 1' from wall
The HLL will be moved to each level as work progresses
Floor joists 2 x 8 Fir
Floor joists 2 x 8 Fir
2x8 Fir floor/roof/deck joist
FALLTECH BOLT-ON D-RING ANCHOR
- Installed with 2 - 9/16" x 3" Grade 8 Steel bolts
- Steel Fender washer on nut side
- Standard steel 9/16" washer on D-ring side
- Nylon-insert lock nut
- A New Nylon-insert luck nut will be used
each time D-rings are installed on new level.
3'
1'
8" TRUE
Center Joist
Attachment of FALLTECH BOLT-ON D-RING ANCHOR
Mounted Center Joist Height
2x8 Fir end jost
2x8 Fir end jost
Exterior wall
HLL Attachment Point View
Deck
Deck
Deck
This is roof, will not need to go higher then this
2x8 Fir floor/roof/deck joist
3'
1'
8" TRUE
Center Joist
Attachment of FALLTECH BOLT-ON D-RING ANCHOR
Mounted Center Joist Height
HLL Attachment Point View
Exterior wall
Deck/Ceiling to next deck
Deck/Ceiling to next deck
Railing system
Alex's proposal
Front View
Rim joists
Field joists
Rim joists
END joist
END joist